CITY OF HALLANDALE BEACH
MEMORANDUM
DATE: May 18, 2007
TO: D. Mike Good, City Manager
FROM: Earl S. King III, Acting Director of Public Works, Utilities and Engineering
SUBJECT: Request to Award RFQ # FY2005-2006-007, Engineering Design and Construction
Services for Installation of a Liquid Chlorination System. BP #019/04
SUMMARY
Pursuant to Chapter 23, Sections 23-226 through 23-228, Design Build Procurement Method, Hallandale Beach Code of Ordinances, request authorization to award RFQ #FY2005-2006-007, Engineering Design and Construction Services for Installation of a Liquid Chlorination System to GlobalTech, Inc. in the total amount of $241,380.00.
===================================================================
F I N A N C I A L D A T A
1. DEPARTMENT: Public Works, Utilities & Engineering
2. DIVISION: Water Production
3. FUND: Water, Renewal Replacement and Community Redevelopment Agency, Public Works
Programs
4. ACCOUNT #: 430-3395-533-6629 & 130-6340-559-6629
5. ACCT. DESCRIPTION: Improvement and Extensions
6. FY BUDGET: FY 2006-2007
7. AMOUNT BUDGETED: $249,318.00
8. GRANT FUNDS: YES_ _ NO_X _ AMOUNT ________
9. FUND TRANSFER: YES___ NO_X_AMOUNT $___________
10. FROM ACCT. #: N/A
11. TO ACCT. #: N/A
12. REASON FUNDS AVAILABLE FOR TRANSFER: N/A______________________
____________________________________________________________________
13. PRICE ANALYSIS: ATTACHED___ ADD'L MAT FDR__ _ NONE_ __
===================================================================
B I D I T E M D A T A
14. DESCRIPTION OF BID ITEM: * _______________________________________
____________________________________________________________________
15. SUPPLEMENTAL MATERIAL: ATTACHED__ ADD'L MAT FDR____ NONE
16. # RFQs SENT: 16
17. # RFQs RECEIVED: 1
18. # RESPONSIVE RFQs: 1*
19. RECOMMENDED VENDOR: _ GlobalTech, Inc. of Boca Raton, FL__*___________
20. RFQ AWARD AMOUNT: $241,380.00 *
21. COMMENTS: *
22. ESTIMATED QUANTITY TO BE PURCHASED (BULK ITEMS): _N/A___________
23. ESTIMATED PURCHASE AMOUNT: ___N/A_______
24. BID TABULATION ATTACHED: YES_ _ NO__X_ ADD'L MAT FDR___
25. TERM OF CONTRACT: N/A
26. BID VALID TO: Completion
27. BID PRICE VALID FOR TERM OF CONTRACT: YES_X_ NO___ COMMENTS___
28. WARRANTY PERIOD: One Year from completion of installation
29. DELIVERY TIME: 150 days from notice to proceed
30. STATE CONTRACT: YES___ NO_X_
31. CONTRACT #: N/A
32. CO-OP PURCHASE: YES___ NO_X_
33. AGENCY: N/A
34. EXPECTED LIFE OF ITEM: 30 years
35. ITEM DEMO'D: YES___ NO_X_
36. REFERENCES CHECKED: YES_X *_ NO___ N/A___
37. CONTRACT: ATTACHED___ ADD'l MAT FDR_ __ N/A__
38. CONTRACT APPROVED FOR LEGAL SUFFICIENCY: YES_ _ NO___ N/A_ X__
39. CURRENT VENDOR: ___N/A___________________________________________
40. CURRENT PRICE: ___N/A___________________________________________
* See corresponding comment on Attachment 1, RFQ Comments
===================================================================
REPORT PREPARED BY: ___________________________ ____________
Hal Elsasser Date Engineer I
Superintendent, Water Production
REVIEWED & SUBMITTED BY: ___________________________ ____________
Earl S. King III Date
Acting Director, Public Works, Utilities & Engineering
REVIEWED AND CONCUR: _________________________________ __________
D. Mike Good, City Manager Date
COMMENTS: ___________________________________________________________
______________________________________________________________________
______________________________________________________________________
______________________________________________________________________
ATTACHMENT 1
RFQ SUMMARY COMMENTS
RFQ #FY2005-2006-007
The following comments relate to the '*' items in numerical order indicated on the Bid Award Summary Memorandum.
14. This project entails conversion of the current gas chlorination system to a liquid
chlorination system. This will result in a reduced risk to the community and increase the
safety of the system operation as gas is more hazardous than the liquid.
18, 19, 20 and 21. The small size of this project influenced the number of bidders.
GlobalTech, Inc. of Boca Raton was the only responder. Staff negotiated the price from
$293,540 to $241,380 and is satisfied that this is a reasonable cost without reducing the
required scope of services.
36. Staff contacted Mike Bailey, Utilities Director in Cooper City: GlobalTech
performed a design-build hypochlorite system for Cooper City. According to Mr. Bailey, Cooper City was very pleased with GlobalTech’s performance. They were professional, reliable and responsive.
REPORT PREPARED BY: ___________________________ ____________
Hal Elsasser Date Engineer I
Superintendent, Water Production